As a frequent commuter on Reservoir, I welcome the news of Reservoir St getting some updates. The city plans on updating Reservoir St from the county line all the way to University Boulevard. A&J Development and Excavating won the project for $10,139,986.49. The project should begin soon and be completed by December 2017.
Phase 1
Phase 1 will begin between University Blvd and Neff Ave. The phase will widen the roadway into 5 lanes including a center turning lane.

From Neff to the County Line
After phase 1, the city will continue to work on Reservoir St from Neff to the county line. This stretch will have 4 lanes and a center median and turning lanes.

For more information, please visit the city website.Source: http://www.harrisonburgva.gov/reservoir-street#Update